Analysis of Project Performance Using Earned Value Analysis through Fuzzy Approach SANDHYA SURESH1, GANAPATHY RAMASAMY2 1Student, Department of Civil Engineering, SRM University, Chennai, INDIA) Email: sandhya.suresh044@gmail.com 2Assistant Professor, Department of Civil Engineering, SRM University, Chennai, INDIA Email: ganapathyramasamy19@gmail.com Abstract: Construction industries are facing challenges day by day. Amidst all these challenges it is very crucial to improve the performance of a project with respect to Schedule and Cost. Earned Value Analysis is an important tool in analyzing the performance of any construction project. It measures the project progress and helps in identifying the critical activities and helps in bringing …show more content…
3. Scope of the Project: Earned Value Analysis as a performance evaluation tool can be used for any construction project. This paper focuses on the Earned Value Analysis done on a real time project. The analysis helped the project perform better through the cost and schedule indices. 4. Earned Value Analysis: There are mainly three terms which identifies Earned Value Technique: Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) Budgeted Cost of Work Performed (BCWP) or Earned Value (EV) Actual Cost of Work Performed (ACWP) or Actual Cost (AC) Planned Value The planned value is that portion of the approved total cost estimate which is planned to be spent on an activity during a given period. PV = Physical Work + Approved Budget Actual Cost Actual cost (AC), also called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period. Earned Value The earned value (EV), also called the budgeted cost of work performed (BCWP), is an approximation of the value of the physical work actually completed. It relates the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to …show more content…
Figure 4 shows the Cash flow report and Figure 5 shows the Budget Cost Report and Figure 6 shows the bar representation of sequence of activities. Fig 4: Sequence of activities The analysis is shown in figure 5 and figure 6. Fig 5: EV cost analysis Fig 6: EV schedule analysis From the Cost Analysis, CV is showing a negative value which means it is over budget. CPI = 0.97, which means the project is getting only 0.97 of every 1 rupee that it spends. From the Schedule Analysis, SV is showing a positive value which means it is ahead of schedule. For the project, initial estimate was based on the plan of individual footings for each column. But there was a change in plan and pile foundation was adopted. This was because of future plans of further raise of this G + 2 level project. Because of this change in plan and a constraint of project deadline (June 2015), they had to work 24 hours a day in the site. This might be the reason for the SV showing a positive value thus telling that project is ahead of schedule. Table 3: Conclusion based on Fuzzy output State of (CPI) ̃ and SPI against 1 Graphical Description Decision making d <
Usually, budgeting is based on tangible cost of products purchased but during this project the main costing was based on man hours. Even the cost benefit analysis of the project was based on man hours involved in the current implementation versus what it would be with the new system in place. - Formative and Summative Assessment – Quality Assurance was a new concept that I learned is critical to the successful implementation of the project. I was not entirely satisfied with this part of the project because there is always scope for more quality control measures but the project was limited by time and cost. For example, peer reviews of code could have help bring up the quality of the coding practices of developers but there was no time to implement that in this project.
Final Project Assessment and Intervention: Dan Dunne from Half Nelson The diversity and scope of individuals’ experiences with addiction is infinite; addiction targets all walks of life, regardless of age, gender, socioeconomic status, etc. Addiction itself manifests in a variety of contexts in a person’s life, including inter- and intrapersonal function, employment, social, and environment, and observable changes can offer clues and insights into progression, severity, and levels of needed treatment (Wahler & Otis, 2014). To properly aid in the treatment and recovery of individuals with substance use disorders, counselors must employ a variety of effective tools and insights, to effectively align an individual’s addiction with a complete diagnostic
The total value of the firm has been calculated with the help of PV of cash flows and the continuing value and it shows an amount of
Wilkerson is currently using the traditional costing system. “Companies that use the traditional costing method assume that the volume metric is the underlying driver of manufacturing overhead cost.” Traditional product costing was established when direct material costs and direct labor costs accounted for the bulk of product costs incurred inside a firm. In the Wilkerson company, materials and labor costs are centered around the prices of materials and labor rates.
With a total slack of 179 days, the detailed marketing plan is the activity with the greatest amount of slack. This means that this activity can be delayed for 179 days without causing delay to the project. Sensitivity The network is relatively insensitive because it has one critical path and there is slack among various activities.
All projects must come to an end and that is the time when it is handed off to the client for their responsibility. For this project there was some road blocks encountered when I was getting to the final stages of the project. I can see how scope creep can extend the timeframe of a project or even derail it completely. This report will describe the timing and extra procedures it took to finalize my project and complete it on time. I planned to have the exit meeting on Monday the nineteenth of October but received no response from the client.
Project Phase: This determines the kind of project being undertaken. It could be a new construction or an already existing building. Setting this parameter aids in the considerations during the energy analysis. Silver Space Tolerance:
The success of the project can be measured through the following ways: - Setting measureables/ performance indicators and deliverables for each of the activities in the project, and then gauging how far have they been
By being fully aware of its function and implications is an important aspect of the project manager’s role and responsibility. The triple constraint is meant to be an asset to the project manager’s arsenal and should not be viewed as a hindrance. This assignment has shown about how and the importance of comprehensive evaluation on the Triple Constraint (Time, Cost, Scope) in a project under uncertainty situation. We introduce an index called as Project Reliability.
Also, various methods of controlling costs such as standard costing system and flexible budgets have close relation with the variable costing system, in turn making it easy to use those methods. 3. Companies using variable costing system are able to prepare income statement in contribution margin format that provides necessary information for cost volume profit (CVP) analysis. On the flip side, this data cannot be directly obtained from a traditional income statement prepared under absorption costing
Given the risk considerations provided in the RCD tool and the Portfolio Theory, the next step should be understanding the available risk/return metrics and determining an optimal mix of assets. Risk Metrics and Advantage/Disadvantages There are two risk metrics used in the model, Conditional Tail Expectation (CTE) and Value at Risk (VaR). These two metrics both look at the tail of the distribution. VaR is a measure of particularly poor outcomes in a stochastic projection. Its major shortcoming is its lack of statistical coherency.
Introduction: The term 'advanced development technology ' in construction industry covers an extensive variety of present day techniques and practices that envelop the most recent improvements in materials technology, design methodology, amount studying, offices management, administrations, structural examination and design, and management skills used in construction industry. Technological advancements in different fields such as medical industry, business industry, electrical engineering, mechanical engineering, civil engineering etc. have brought many positive impacts. Fusing advanced development technology into construction industry can expand levels of value, proficiency, safety, maintainability and incentive for money. The advanced technologies in construction industry are very useful for all type of small and large scale construction projects.
Moreover, while planning and executing personnel budgeting, wages, bonuses, commissions and incentives apart from the employer-paid costs are deliberated by financial committee and managers to devise sound and comprehensive budgeting
Mid-Term Paper – Boeing Analysis MGMT 658 Abstract Unlike other manufacturing industries, aircraft manufacturing is considerably large and complicated. It is a field with high risk involvement. Losses incurred can be quite huge due to the size of the industry. Being the case, the aircraft manufacturing industry calls for intrinsic planning and comparatively larger pool of skilled and cooperative manpower for successful production.
As shown in the Figure 1, there is a lack of dates from 20th July to 29th July. The reason for this is the need and focus on learning the language which will be used in almost all projects: Ruby on Rails. The general project management is very clear in its schedules, tasks and milestones as seen in the figures above. 1.1.