Summary Dura (Aust) Constructions Pty Ltd v Hue Boutique Living Pty Ltd6 • To be valid, a show cause notice must comply with the requirements of the contract under which it is issued and convey to the reader what is amiss. • Detailed particulars are not necessarily required for a valid show cause notice. • The level of detail required in a show cause notice depends on a number of factors including the type of breach and the response to be given by the contractor. More detail would be required for a self-executing notice to rectify (which is not a concept found in AS 2124). • In Victoria, courts are unlikely to imply a term of reasonableness when issuing a show cause notice or evaluating whether cause has been shown. The opposite approach has …show more content…
The principal engaged the contractor under an AS 2124 – 1992 (Construct only) form of contract. Eighteen months into the project, the principal expressed concern regarding what it said was the slow progress, poor quality of the works and the quantum of progress claims submitted by the contractor. Accordingly, the principal served four show cause notices on the contractor under the contract, alleging that the contractor was in default by separate substantial breaches of the contract and requiring the contractor to show cause (in writing) why the principal should not: 1. Take the whole or part of the remaining work out of the contractor’s hands; or 2. Terminate the contract. Under the contract, the show cause notices must (among other things) specify the alleged substantial breach. The allegations of substantial breach made against the contractor in the show cause notices were that, among other things, it had failed to: 1. Proceed with the works with due expedition and without delay; 2. Comply with directions of the superintendent; and 3. Use the standard of materials or workmanship required by the …show more content…
Disputes arose between the parties regarding defects and incomplete work. The dispute came to a head when Cordon required Lesdor to sign the strata plan in order for it to start selling units and realising its return. Lesdor refused to sign the strata plan, arguing that it did not have to do so until Cordon had fully completed construction according to the plans and specifications. There was no definition of “Completion” in the contract. Lesdor terminated the joint venture agreement with Cordon on the basis of Cordon’s unwillingness to properly complete the work and claimed damages for defective work. Cordon commenced proceedings against Lesdor on the basis that Lesdor’s purported termination amounted to repudiation and claimed damages for resulting loss. Lesdor cross-claimed for damages resulting from Cordon’s defective work. Finding The Court found that the works had not achieved “completion” which the Court interpreted to mean “full completion”. Accordingly, Lesdor was not required to sign the strata plan and, following Cordon’s unwillingness to properly complete the work, Lesdor had lawfully terminated the
The Board of Directors, of the Pinion Ridge Homeowners Association. having duly noticed and convened a meeting of the board pursuant to Elizabeth Tuttle’s rental house Whereas circumstances have arisen that indicate to the board that Elizabeth Tuttle did not apply for any building permits through San Miguel county or the state of New Mexico to remodel a shop .An apartment was built in its place .whereas having duly deliberated on and investigated the covenants of association forbids a second building to be built on a single duelling. The board adopts the following resolution to be inserted in the minutes of the meeting It is hereby resolved owner shall not rent or lease the apartment building .Elizabeth Tuttle must disconnect the main water
In addition, the final summary judgment contains no set off for the amount of the restitution ordered. Further, there is nothing in the record to establish that the damages awarded in the final summary judgment compensate Therma Builders for damages not already awarded in the restitution order (FindLaw's). The final summary judgement was affirmed in part; reversed in part; and remanded for further
This essay will be organized by answering the questions in chronological order; to which in the first question, I will be looking heavily into the case of R.v. Saulte Ste. Marie and Roach. It will incorporate the regulatory offences and the mental blameworthiness and how strict liability acts as a balance between the two. It will also include the defence of due diligence.
_ Good Cause document was very generic and did not clearly explain the good cause reason why the rep payee had submitted late filing of CDR hearing appeal. missing in good cause letter was rep payee was actively pursuing an appeal with section 301 and after further clarification from the office D47 she decided to request a hearing request with good cause.
Moreover, it would carry out an undue hardship that even with the accommodation. Turner would still be unable to perform work on lines 8 and 9. This matter should be used by a jury based upon the completely developed evidence
Mr. Haselton was writing this document because the defendants were appealing the court
NEGLIGENCE, CASES,SOLUTION CASE STUDY Brickhill v Cooke [1984] 3 NSWLR 396 Facts • The prospective purchasers of a property engaged an engineer to inspect the property and prepare a written report. • The engineer concluded that the property was structurally sound.
The Defendant, as the Airport operator directly and vicariously caused foreseeable harm to Plaintiff by, among other things: a) negligently failing to supervise daily operations of the Airport according to the Federal Aviation Regulations and due diligence. b) failing to provide correct information and intentionally concealing and falsifying the information on the company’s website and by doing so failing to warn Plaintiff and others of the risk associated with the violations of the Code of Federal Regulations 4CFR 91 119, while Defendant had a duty to disclose the wrongdoing and potential harm; c) negligently failing to report violations to the Federal Aviation Administration and governmental agencies responsible for public welfare and
FACTS In December of 1990, Gerry DiNardo was hired as the head football coach by and for Vanderbilt University under a five-year contract. Under this contract, “liquidated damage provisions” were outlined for both parties, with section 8 of the employment contract specifically detailing the liquidated damages he should owe to the plaintiff/appellee should he terminate his five-year contract with Vanderbilt and be “employed or performing services for a person or institution other than the University” within the five-year term of the aforementioned contract. In August of 1994, the Athletic Director for the University, Paul Hoolahan, offered the defendant/appellant a two-year extension of the contract. An addendum was drawn up by Vanderbilt’s Deputy General Counsel that would extend
The Independent Contractor (“QIC”), Services, reviewed the Appellant’s claim and issued an unfavorable reconsideration decision on August 9, 2013. The QIC held the Appellant responsible for payment of
3.1. Termination with Cure. This Agreement may be terminated by either party upon thirty (30) days written notice, if the other party commits Material Breach, as defined for each party in Sections 3.1(a) and 3.1(b), or fails to perform or comply with any of the material terms, covenants, or conditions of this Agreement, and such failure is not cured within such thirty (30) days notification period. There will be no termination fee allowed for entire Section 3.1.
Teresa's case was submitted to the jury on the counts alleging breach of contract, negligence and wantonness, and the tort of outrage. The jury returned a verdict against Akins and in favor of both plaintiffs. The jury assessed compensatory damages at $450,000 and punitive damages at $150,000, for a total of $600,000 in Megan's case; in Teresa's case, the jury assessed compensatory damages of $200,000 and punitive damages of $150,000, for a total of $350,000.”
ASSESSMENT TWO A. ISSUES Given that Emma relied on information from the wrong page of the brochure while entering into an agreement with Richard, is the contract affected (whether valid, void or voidable) by the mistake of facts? Is the promise by George to let off Richard from paying the rent increase in the following year valid and enforceable despite the express provision in the lease? What was the effect of Richard’s counter-offer to the offer made by Tom to purchase the car at $18500?
The court argued that Koon could have made the same statement without imitating Roger’s work. Koon had to pay compensation to Rodgers. CAN OR CANNOT PROTECT WORK AND
Failure started by accepting the lowest cost bid, missing the actual cost of the project. The bid was so low that before the contract was signed, the cost of the project rose by 36%, and the project had not even started.