6.3.1.8 Ranking of Factors that Causes Delays
In table 6.9 the overall ranking of factors that causes delays in construction of Hydropower projects have been established based on the result of analysis of factors in each group.
Table 6.9: Ranking of factors that causes delays
Factors Contractor Consultant Overall Index Index Index Index
Delay in approval of Bid Documents/ Design Specifications 3.78 3.51 3.69 1
Modification/ increase in scope of work 3.70 3.43 3.58 2
Delay in approval of Detailed Engineering Drawings & Construction Materials 3.62 3.12 3.43 3
Lack of prompt decision making 3.29 3.48 3.38 4
Delay in giving land acquisition to the contractor 3.09 3.37 3.25 5
Delay in payment of contractors invoices 2.86 3.43 3.21 6
…show more content…
In order to identify the effect of delays in hydropower construction project, there are factors that effects delays were identified and ranked based on the mean value which calculates the average indexes of factors between contractor and consultant, as shown in Table 6.10. Referring to Table 6.10 and Figure 6.11, shows time overrun and cost overrun were the two most common effects of delays in construction project from the view of point of contractor and consultant. According to the top ten factors that contributed to the causes of delays, there are at least five factors having high influence that caused of time overrun in construction project such as delay in approval of bid documents/design specifications, delays in sub-contractors work, modification/ increase in scope of work and conflicts in sub-contractors schedule in execution of project. For cost overrun, there are also contain at least five factors having high influence in construction project, such as lack communication and coordination, change orders by client during construction, inadequate contractor’s work, ineffective planning and scheduling of project, and mistakes and discrepancies in design …show more content…
These methods are ranked based on the mean value which calculates the average indexes of method identified by the contractor and consultant. The result of research revealed that the effective site activities, effective planning & execution, clear correspondence channels, working with collaboration in construction and proper planning and scheduling has made the top five effective for overall ranked by contractors and consultants.
The site management and supervision is the most important factor among the fifteen factors. In construction, we need to ensure the coordination among the various personnel’s, supervise quality and standard, and ensure that the contractors meets the required timelines to achieve mile stones, avoiding shortcuts or deviate from restraints. Besides that, the project directors and managers also need to ensure that the material used is according to the contract and according to
I am making this appeal in response to the sanction that is imposed on me in reference to the case #3788. The hearing panel found me guilty on the charge of complicity in the course of construction scheduling COSC 603:299 and awarded me a grade of F* in the course COSC 603:699 Construction Scheduling for which I was enrolled in Spring 2015 semester. The basis of my appeal is that the sanction on me is not commensurate to the violation. I would like to provide the following rationale for my defense.
Our commitment is to deliver projects that are of high quality, timely and
For example floods were a big part to the development of the project. This was a hard problem for the developers building the project, it was hard for them to overcome this. As this quote states “One major flood occurred in 1912. A larger flood hit the Yuma Project in 1916, breaking previous records. Flood water from the Gila River began rising on January 18, 1916, and by January 22 flowed over the lower Reservation levee causing 800 feet in breaks”.
The octagonal dome of Santa Maria del Fiore in Florence was built from Filippo Brunelleschi, of early Renaissance entirely as a self-supporting structure . This precision structure would be difficult to re-create today, even with modern and specialized tools, so it is one of the most studied historic structures. Massimo Ricci, Barry Jones and Andrea Sereni had a question: How Filippo Brunelleschi built the Dome?
D.B. Gulliver & Son Roofing of Hinesville, GA is a locally owned and operated residential roofing company that holds their work to the highest standards. They do emergency jobs when necessary and work with most insurance companies, so anyone looking for the best in local roofing companies will be in good hands. Thanks to the breadth of their services, which include roof installation, roof repair, and re-roofing, they're familiar with all types of materials and the average lifespan of a roof. There are a handful of factors at play when it comes to determining a roof's lifespan. From the climate to the design, installation quality, and more, you'll want to take everything into consideration.
Address any variances in budget reporting from previous reporting period. Include: (1) Estimated Total Project Budget, (2) Estimated Construction Budget, and (3) Dollars Expended to Date. If there is a Financing Agreement for this project, provide an update. If none, indicate that. Section 5 – Project Scope and/or Quality Items Indicate any adjustments or considerations that impact or change the project scope or quality (such as pending change orders, standards waivers, etc.)
There is a lengthy contract approval process
Describe the auspices of your agency (i.e. public, private-non-profit, proprietary, etc.) BUILD is a non-for profit 401c3 agency that consist of many high impact programs to help improve the lives of the at risk youth in the communities it serves. All funds that are donated or earned at BUILD is used to successfully pursue the organizations mission.
Introduction In today’s world, most developing countries are in a race to build up the necessary infrastructure to scale up there operations and become the next global superpower. In this process, a lot of energy is consumed – be it for transportation, manufacturing or construction. This rapid growth of energy use seen over the past two decades have raised concerns for governments and energy-related organizations alike. Questions with regard to the supply, sustainability and exhaustion of energy sources abound, and while most developed countries have taken active steps to reduce consumption of scarce resources, the position of developing countries in this regard is still lacking.
Clients often need to be made to realize that if a project is to be completed at a certain level of quality, then a certain amount of time and money need also to be invested in the project. Projects that have time restrictions will need to increase the resources assigned to it or have the quality or scope reduced. The well known triple constraint formula is Cost * Schedule= Quality.
CHAPTER 5 CONCLUSION 5.1 Introduction The impact of recession has been felt throughout the world. This study is an effort to analyse the impact of the recession in India, especially in the construction industry. The impact of the recession has been different in countries around the world. The way the recession has affected the various industries of each nation is also different.
1. Thesis Title Nuclear energy: it's efficiency sufficient to justify danger? 2. Thesis Description Thesis statement: Although nuclear energy has been proposed as a solution for our energy requirements it is not reliable because of issues regarding safety, nuclear waste storage. It is possible in a medium-long period of time to replace it with renewable energies.
Introduction: The term 'advanced development technology ' in construction industry covers an extensive variety of present day techniques and practices that envelop the most recent improvements in materials technology, design methodology, amount studying, offices management, administrations, structural examination and design, and management skills used in construction industry. Technological advancements in different fields such as medical industry, business industry, electrical engineering, mechanical engineering, civil engineering etc. have brought many positive impacts. Fusing advanced development technology into construction industry can expand levels of value, proficiency, safety, maintainability and incentive for money. The advanced technologies in construction industry are very useful for all type of small and large scale construction projects.
Decorative Choices For Your New Concrete Driveway If you 're tired of the maintenance needs of a dirt or gravel driveway, then it 's time to consider installing something more permanent. One option is concrete. Concrete driveways are durable and they can be stylish too. You generally have more options with concrete than you do with asphalt since concrete is lighter in color and can be dyed easily.
An introduction to highway building: Although there are many methods to constructing a road, all are based on the principle that geographical objects are removed and replaced with harder and more wear-resistant materials. The pre-existing rock and earth is removed by digging or explosions. Tunnels, embankments and bridge are then added when necessary. The material that the road is being constructed from is then laid by various pieces of equipment, which will be looked at in greater detail in this assignment. The construction management of roads has become increasingly more difficult as larger structures are constantly being required in increasingly short amounts of time.